CIP Monthly Status Report – January 2019

Digesters under construction
In January, the Fire Life Safety Upgrades Project passed Stage Gate 3: Authorization to Proceed. The project team began preliminary design, which is expected to be completed by summer 2019. The Digester and Thickener Facilities Upgrade Project completed the roof concrete placement on Digester 5 and continued roof replacement work on the remaining three digesters.

The Cogeneration Facility achieved 50 percent height on the main building walls, which are anticipated to be completed in April 2019.

The City held a pre-construction meeting for the Blower Improvements Project with all stakeholders and issued the Notice to Proceed to the contractor, Monterey Mechanical.

The Headworks Project team completed contract development and cost negotiations for the exploratory trenching and subsurface investigations, which are anticipated to be performe¬¬d in April. The design-builder submitted the Basis of Design Report and conducted a review workshop with the City.

For the Digested Sludge Dewatering Facility Project, the City interviewed three proposers for the design-build entity selection process and issued the Notice of Final Ranking at the end of the month. The City will begin negotiations with the top-ranked firm.