Pavement update week of 6/17/19

Cold in place recycling

We're continuing to wrap up weather-delayed 2018 projects on Santa Teresa Boulevard, Blossom Hill Road, and San Carlos Street.

  • Striping will continue on Santa Teresa Boulevard and begin on Blossom Hill Road.
  • Cold-in-place recycling will continue on San Carlos Street, then later this week hot asphalt will go down.
Get the weekly pavement update delivered straight to your email inbox! Visit our Notify Me page and scroll down to Transportation>Pavement to subscribe.

Activity

M

Tu

W

Th

F

Sa

Su

M

Tu

W

Th

F

6/17

6/18

6/19

6/20

6/21

6/22

6/23

6/24

6/25

6/26

6/27

6/28

Santa Teresa Bl (Cottle Rd - Dunn Av) - CD 2

Striping

x

x

 

 

 

 

 

 

 

 

 

 

Blossom Hill Rd (Meridian Av - Almaden Ex) - CD 9, 10

Striping

 

 

 

x

x

 

 

x

x

 

 

 

San Carlos St (Leigh Av - Lincoln Av) - CD 6

Wedge Cut/Conform

x

 

 

 

 

 

 

 

 

 

 

 

4"CIR

x

x

x

 

 

 

 

 

 

 

 

 

Asphalt Overlay

 

 

 

x

x

 

 

 

 

 

 

 


Glossary

Asphalt overlay: Adding hot asphalt back to the street as part of the resurfacing process.

Cold-in-place (CIR) recycling: The process of removing the existing asphalt surface, mixing the crushed asphalt with a recycling agent, and reapplying the mixture back on the street surface.

Micro milling: The process of removing a thin top layer of failing asphalt.

Remove and replace: The process of cutting segments of damaged, warped, or collapsed asphalt out of the roadway and filling them back in before resurfacing or sealing begins.

Wedge cut/Conform cut:  Removing the thin portion of the street adjacent to the curb line in order to allow for the smooth application of pavement material to the edge of the street.

Striping: Adding lane lines or other markings to the street surface.
Facebook Twitter Google Plus Email

Other News in Transportation > Pavement

Pavement update week of 8/12/19

Posted on: August 12, 2019

Pavement update week of 8/5/19

Posted on: August 5, 2019

Pavement update week of 7/29/19

Posted on: July 29, 2019

Pavement update week of 7/22/19

Posted on: July 22, 2019

Pavement update week of 7/8/19

Posted on: July 8, 2019

Pavement update week of 7/1/19

Posted on: July 1, 2019
Cold in place recycling

Pavement update week of 6/24/19

Posted on: June 24, 2019
Cold in place recycling

Pavement update week of 6/10/19

Posted on: June 10, 2019
Cold in place recycling

Pavement update week of 6/3/19

Posted on: June 3, 2019
Orange steamroller

Pavement update week of 5/27/19

Posted on: May 27, 2019

Record-Breaking Paving in 2019

Posted on: March 26, 2019